back to projectsEast Lancashire Hospice

Category Healthcare,
ClientEast Lancashire Hospice
Value£1.06 million
ConsultantsStanton Andrews Architects
CompletionDecember 2018

The East Lancashire Hospice project was a combination of new build and refurbishment across 5 phases of works over a 56 week contract.

Phase 1 was to refurbish and extend the existing dining area to form a new catering kitchen / café area with seating and recreational spaces within the dining area. Phases 2 and 3 were the formation of new staff offices, staff facilities and to upgrade the new staircase with granite stair treads and glass balustrades. Phase 4 was to form a contemplation room and craft room with very intricate details to the contemplation room being fully round. Phase 5 was to extend two patient / family bedroom facilities to provide more space for loved ones to spend quality time with patients.

The project was extremely challenging due to the hospice staying live at all times, therefore careful consideration had to be given at all times. Lyn Stevenson Chief Executive of East Lancashire Hospice gave a special thanks to Project Manager Nick Pinington for his hard work, pragmatic approach and diligence during the project and thanked the Pinington team for the hard work and effort to achieve such a fantastic space.

Similar Projects

Stroke Therapy Royal Lancaster Infirmary

As part of our ongoing works with Morecambe Bay NHS Trust the Royal Lancaster Infirmary new Stroke Therapy Extension was the latest in a long list of collaborative projects. This project took meticulous planning from a design, procurement and execution perspective due to the location of the works. The work site was within an existing […]

read more

Royal Lancaster Infirmary Ward 50 Diabetes Unit

Pinington were appointed as main building contractor to undertake the new Diabetes unit which included an extensive internal refurbishment and remodelling to an existing physiotherapy ward and a new entrance extension forming a lobby and extended waiting area. The works included an extensive demolition and alterations period and incorporated vast amounts of new M&E equipment […]

read more

Westmorland General Hospital Water Tanks

Pinington Ltd were appointed to undertake a large scale upgrade of the existing backup water tanks and plate heat exchanger to Westmorland General Hospital Kendal.   The works comprised of the removal of the existing external water tanks, the erection of a new build masonry and cladded building to house the new water tanks and […]

read more

Carnforth Free Methodist Centre

Carnforth Free Methodist Centre proved to be our second church / conference centre handover in January 2022. Again another project hampered and hamstrung by the Covid19 pandemic got off to a slow start however very quickly ramped up to provide a fantastic facility for all involved. Our first involvement when tendering this project was to […]

read more