Furness General Hospital Ambulatory Care Phase 1 Handover

Phase 1 of our latest project for Morecambe Bay NHS handed over this morning after a successful start to the project.

 

The flagship project is approximately £1.1 million pounds of a refurbishment to the existing ward to included new air handling plant, ventilation and complete new treatment and consulting rooms split into 6 phases. The phasing of the project has been extremely complex due to the need to keep the ward running during the works and has been carefully planned out between the trust, project architects Mellor Architects and Pinington. The last phase of the project is due to hand over in October 2021 based on the current programme.

 

On the handover of phase 1 Morecambe bay NHS tweeted:

Phase 1 of ACU FGH has been handed over Heavy check mark It is always challenging working in a live department but ACU staff and patients have been very understanding and flexible. On to phase 2 of 6…

#DesignTeam

Keep an eye out for news on completion of other phases in the coming months!