back to projectsWest Kirby Grammar School Science Lab Refurb

Category Education,
Laboratory Work,
ClientWest Kirby Grammar School
Value£475,000.00
ConsultantsSurveyors to Education
CompletionAugust 2019

Pinington were appointed as main contractor to undertake the full strip out and refit of 4nr science laboratories and 2nr prep rooms.

The works included strip out of all existing fixtures and fittings along with M&E services with new flooring, suspended ceilings, decoration, fully re-wired electrically with new LED lighting, Gas pipework and vulcathene science lab drainage. The science laboratory furniture was then supplied and fitted by Klick Technology.

The works were undertaken over a 14 week period with the first 7 weeks of the project working around the half term of school and were complete on time and on budget with the client very happy at the end of the project.

Similar Projects

Barrow Sixth Form College

Pinington were appointed to complete a complex and challenging refurbishment to a full teaching block at Barrow Sixth Form College. The works were split into 3 phases with only 1 phase of works live at any one time. However while undertaking the works the remaining areas of the block stayed live so carefully planning and […]

read more

Bleasdale School Refurbishment

The project involved the refurbishment of the classrooms and toilets at the community school that offers facilities to those most in need. Bleasdale School is an Outstanding school in the centre of the picturesque village of Silverdale in an Area of Outstanding Natural Beauty. The day school includes two buildings with a rich history on […]

read more

Carnforth Free Methodist Centre

Carnforth Free Methodist Centre proved to be our second church / conference centre handover in January 2022. Again another project hampered and hamstrung by the Covid19 pandemic got off to a slow start however very quickly ramped up to provide a fantastic facility for all involved. Our first involvement when tendering this project was to […]

read more

St Thomas Church Lancaster

Pinington Limited were appointed as main contractor on this prestigious “Lancaster Heart of the City Project” prior to the Covid19 pandemic in early 2019 which unfortunately delayed the start of the project. When the the pandemic restrictions started to release the works subsequently started based on the original tender. The works included demolition of parts […]

read more

Contact Us

Please use the form to contact us. By filling out this form, you are agreeing for us to use your details to contact you. We will only use this information to support your enquiry and it will not be used for any other purpose.