back to projectsAmbulatory Care Unit Furness General Hospital

Category Healthcare,
ClientUniversity Hospitals of Morecambe Bay NHS Trust
Value£1,135,000.00
ConsultantsMellor Architects
CompletionNovember 2021

The flagship project was a refurbishment to the existing Ambulatory Care Unit at Furness General Hospital.

 

The works consisted of a full new air handling plant, ventilation which mean an new plantroom had to be built within a land locked internal courtyard. Complete new treatment and consulting rooms to provide workable spaces within the ward, domestic sluices and cleaning spaces, drug storage and drugs perpetration areas, a new nurse base and confidential office and finally a new reception desk and nerve centre to the refurbished ward.

 

The phasing of the project was extremely complex due to the need to keep the ward running during the works and was carefully planned out between the trust, project architects Mellor Architects and Pinington. Split into 6 phases this elongated the programme however enabled the unit to stay operational during the construction phases and the relationship forged between the ward staff and the Pinington management team was critical to this project being such a success.

Similar Projects

RLI Maternity Triage Unit & The Willow (Bereavement) Suite

Pinington were appointed by the University Hospitals of Morecambe Bay NHS Foundation Trust to provide the new Maternity Triage Unit and The Willow (Bereavement) Suite. The facility offer increased comfort and faster access to care at some of the most significant times in people’s lives. The Willow Suite with its private courtyard garden will offer […]

read more

Ward 37 Royal Lancaster Infirmary

As part of our ongoing Measured Term Contract with Morecambe Bay NHS Trust we were asked to undertake a full refurbishment to Ward 37 at the Royal Lancaster Infirmary. The existing ward was decanted and moved to a separate ward within the hospital and a very tight timescale was put on the works due to […]

read more

Bleasdale School Refurbishment

The project involved the refurbishment of the classrooms and toilets at the community school that offers facilities to those most in need. Bleasdale School is an Outstanding school in the centre of the picturesque village of Silverdale in an Area of Outstanding Natural Beauty. The day school includes two buildings with a rich history on […]

read more

Westmorland General Hospital Theatre 1, 4, 5 & Recovery

Pinington completed  this multi phase project over a period of 3 years at Westmorland General Hospital. The first phase of works was to undertake a new 4 storey extension to house a new operating theatre, ground floor storage and a 2 storey plantroom specifically built to house all the key and critical M&E plant for […]

read more