back to projectsAmbulatory Care Unit Furness General Hospital

Category Healthcare,
Client University Hospitals of Morecambe Bay NHS Trust
Value £1,135,000.00
Consultants Mellor Architects
Completion November 2021

The flagship project was a refurbishment to the existing Ambulatory Care Unit at Furness General Hospital.

 

The works consisted of a full new air handling plant, ventilation which mean an new plantroom had to be built within a land locked internal courtyard. Complete new treatment and consulting rooms to provide workable spaces within the ward, domestic sluices and cleaning spaces, drug storage and drugs perpetration areas, a new nurse base and confidential office and finally a new reception desk and nerve centre to the refurbished ward.

 

The phasing of the project was extremely complex due to the need to keep the ward running during the works and was carefully planned out between the trust, project architects Mellor Architects and Pinington. Split into 6 phases this elongated the programme however enabled the unit to stay operational during the construction phases and the relationship forged between the ward staff and the Pinington management team was critical to this project being such a success.

Similar Projects

Carnforth Free Methodist Centre

Carnforth Free Methodist Centre proved to be our second church / conference centre handover in January 2022. Again another project hampered and hamstrung by the Covid19 pandemic got off to a slow start however very quickly ramped up to provide a fantastic facility for all involved. Our first involvement when tendering this project was to […]

read more

St Thomas Church Lancaster

Pinington Limited were appointed as main contractor on this prestigious “Lancaster Heart of the City Project” prior to the Covid19 pandemic in early 2019 which unfortunately delayed the start of the project. When the the pandemic restrictions started to release the works subsequently started based on the original tender. The works included demolition of parts […]

read more

Westmorland General Hospital Theatre 3 Refurbishment

Pinington Limited were appointed as main building contractor to undertake a full refurbishment of theatre 3 at Westmorland General Hospital starting in June 2020 and completion in January 2021.   The project was extremely complex due to the location of the existing theatre on site, proximity to other live theatres and complexity of the work […]

read more

Royal Lancaster Infirmary The Ashton Kitchen Servery

Pinington were appointed as main contractor on the high profile fit out and refurbishment of the existing Skylight Kitchen within the Royal Lancaster Infirmary. The works on site involved a complete strip out of the existing servery and formation of a temporary servery to ensure that normal operations could continue within the restaurant area during […]

read more

Contact Us

Please use the form to contact us. By filling out this form, you are agreeing for us to use your details to contact you. We will only use this information to support your enquiry and it will not be used for any other purpose.