Corporate and Social Responsibility

Testimonials

The Caravan Club "The Caravan Club has worked with Pinington Ltd on several major projects over the past 5 years, all were completed on time, within ... ... read more

News

02.05.12 Spring 2012 Pinington helping to spice up business in Lancaster Pinington are delighted to be main sponsors for the new and exciting business networking organisation’s “Networking in the City” launch of the new lunchtime... ... read article
20.12.11 Pinington on Tourer 2012 Caravan Club Project Awards Following recent project and bid successes, we are pleased to inform you of our strengthening of relationship and project portfolio for The Caravan... ... read article
11.11.11 Business Development We are pleased to announce that Ian Powell has been appointed to head up the Business Development of the business. Ian will focus on improving company standards strengthening... ... read article

New Heating Plant and Ancillary Stores, Waddington

Client: 
Girl Guiding Uk
Value: 
£400,000
Location: 
Waddington, Lancashire

This pioneering energy efficient project partly funded by the Carbon Trust delivered a new biomass heating system to replace the separate systems which fed the existing buildings and associated storage buildings at Waddow Hall, Training & Activity Centre just outside Clitheroe.

The works comprised of three separate buildings; new plant room and woodchip store, new garage / workshop and a new storage building together with the installation of new district heating pipework and drainage.

The district heating pipework was pre-insulated plastic pipes buried in the ground linked to all buildings. A back up oil boiler was installed along side the Woodchip Boiler to provide back up to the woodchip boiler in the event of failure or during cold spells. The plant room was linked to a store constructed below ground to provide storage for the woodchip. 

 
The centre was open through out the project which meant phased change over’s onto the new system which were programmed to eliminate any problems with the woodchip boiler prior to the main administration building changing over to the new system.

New Heating Plant and Ancillary Stores, Waddington
New Heating Plant and Ancillary Stores, Waddington
New Heating Plant and Ancillary Stores, Waddington
New Heating Plant and Ancillary Stores, Waddington
New Heating Plant and Ancillary Stores, Waddington
Marketing Agency